Facade Tender: How to Write a Specification and Compare Bids

A facade works tender gives a fair comparison only when all bidders price the same scope. To achieve this, the client prepares a technical specification with the design, an element schedule and material requirements, and compiles the bids into a single table line by line — rather than comparing the totals.

The main criterion for choosing the winner is not the lowest price but the completeness of the bid, realistic deadlines and the contractor's proven ability to manufacture and install the cladding. Price differences between bidders are almost always explained by different scopes of work.

This article is for developers, technical clients and general contractors running a tender for a ventilated facade or cladding in glass fibre reinforced concrete (GFRC), natural stone or porcelain stoneware. Related topics are in the section Facade Design and Selection.

Contents of the Specification

A facade specification should answer the questions that each bidder would otherwise answer in its own way. The minimum contents:

1. General project data: address, use, number of storeys, top level, wind and snow region, site seismicity.

2. Design documentation: architectural drawings (elevations, sections, details), structural data on the load-bearing walls, the facade passport or approved appearance, if any.

3. Scope of work: design of the substructure and shop drawings, supply, installation of substructure, insulation, wind barrier, cladding, junctions, sills, reveals.

4. Material requirements: cladding type by zone, texture, colour, combustibility class, requirements for the substructure and fixings.

5. Site conditions: schedule, work zones, availability of scaffolding or lifts, storage area, power supply.

6. Bidder requirements: experience, own production, installation crews, documents.

7. Bid form: a single table of items in which each bidder must enter prices.

The more detailed the 'scope of work' section, the fewer 'hidden items' will appear after the contract is signed.

Element Schedule

An element schedule is a list of all cladding products with dimensions and quantities. For flat panels it comes down to area by type, while for GFRC or stone decoration it consists of individual items, because the cost of each profiled element is calculated separately.

ItemWhat to specifyExample unit
Flat panelsSizes, thickness, texture, colourm², pcs
Cornices, bands, string coursesProfile (cross-section), length, quantitylinear m
Columns, pilastersHeight, diameter or section, capital and basepcs
Window surroundsOpening size, surround profile, keystoneset
BalustradesBalusters, handrail, plinthlinear m, pcs
Stone plinth claddingRock type, thickness, finishm²

Without a schedule, bidders will price from the picture, and discrepancies in the number of elements will produce price differences unrelated to quality. The schedule can be prepared by a design organisation or the facade contractor at the preliminary design stage.

Comparison table of bids from facade tender participants
Comparison table of bids from facade tender participants

Comparing Bids

Bids are compiled into a comparison table by specification item. The procedure:

• check that every bidder has filled in every line; an empty line means the item is not included;

• compare quantities: if a bidder's area or number of elements differs from the schedule, find out why;

• compare materials: substructure brand, insulation thickness, fixing type, cladding manufacturer;

• compare deadlines by stage and how they fit your schedule;

• record payment terms: advance share, stage payments, retentions.

Separately, assess who does the work: if a bidder manufactures the cladding itself and installs it with its own crews, the risk of a break in the chain is lower than with an intermediary who buys products and hires installers as it goes.

It is useful to reduce all bids to unit rates: cost per square metre of cladding by type, per linear metre of cornice, per window surround set, per square metre of substructure with insulation. This shows which items drive the difference. A sharply lower rate on one item while the rest are at market level usually means an error in quantity or a different material; a sharply higher one means the bidder has priced in the risk of incomplete input data.

If bidders ask many clarifying questions, send the answers to everyone so that bids remain comparable.

Hidden Items

Hidden items are works and materials that were left out of a bid but will inevitably be needed. They are what turns the cheapest bid into the most expensive. Most often omitted:

• substructure design, calculations and shop drawings;

• pull-out tests of anchors in the base wall;

• junctions with windows, sills, reveals, parapets;

• trim and corner elements, fixings, embedded parts for decoration;

• delivery, unloading, storage;

• scaffolding, lifts, aerial platforms, cranes;

• protection of products on site, cleaning;

• as-built documentation.

The safeguard is a clause in the specification: 'the bidder must include in its bid all works and materials required to complete the facade according to the design; costs not stated in the bid will not be paid'. And a mandatory question to each bidder: what is not included in its price.

Choosing the Winner

The winner is chosen on several criteria, not price alone. A reasonable evaluation scheme:

1. compliance of the bid with the specification — bidders with incomplete bids either complete them or drop out;

2. full cost including hidden items;

3. realism of the schedule and production capacity;

4. experience on comparable projects, confirmed by addresses;

5. own production and installation team;

6. payment and contract terms.

Before the final decision, it is useful to negotiate with the two or three best bidders and visit their production. The price of facade works can only be finally fixed after inspecting the site: this is exactly how TECHNOFORMA determines the cost of construction and installation works.

Once the winner is chosen, its bid and answers to questions become an annex to the contract. This fixes the scope of work and prevents disputed items from later being treated as extras.

Schedule of glass fibre reinforced concrete facade decoration elements
Schedule of glass fibre reinforced concrete facade decoration elements

Examples from TECHNOFORMA Projects

For large residential complexes, a tender often covers design, production and installation. An example is the Triumf residential complex in Makhachkala: 12 storeys, 11,500 m² of GFRC cladding, 12.2018–01.2021; TECHNOFORMA Group carried out design and installation.

Another example is the Na Sovetskoy residential complex in Cherkessk: 15 storeys, 6,000 m² of GFRC, 01.2025–07.2025, also design and installation. Other projects with volumes and dates are in the section TECHNOFORMA projects. How to break down the winner's estimate by item is explained in the article Facade Works Estimate: Structure and Review.

FAQ

What should a facade specification include?

Project data, design documentation, scope of work, material requirements, site conditions, bidder requirements and a single bid form.

How do I compare bids for facade works?

Compile them into a table by specification item, check quantities and materials, identify excluded items, and only then compare totals.

Why is an element schedule needed in a tender?

So that all bidders price the same number of products. Without it, price differences reflect different scopes, not different quality.

Why does the cheapest tender bid often turn out more expensive?

It usually omits design, fixings, junctions, equipment or delivery, and these costs appear after the contract is signed.

Can the price be fixed after the tender?

Yes, if the bid is complete and was prepared after studying the design and inspecting the site; otherwise the price will be refined.

Related articles

All articles
How to Choose Facade Cladding: Criteria and Comparison

Facade design and selection

How to Choose Facade Cladding: Criteria and Comparison

How to choose facade cladding: start not with the material but with the conditions: building type and height, load-bearing capacity of the walls, climate, fire safety requirements, local planning regulations, budget and service life. Only then compare materials: natural stone, glass fibre reinforced concrete (GFRC), porcelain stoneware, fibre cement and composite panels, clinker, render and metal cassettes.For multi-storey buildings the main criterion is the system as a whole: cladding, substructure, insulation and fixings must be compatible and permitted for a building of that height and fire hazard class. An attractive slab on an unsuitable substructure is a risk, not a saving.This article is for architects, developers, general contractors and private homeowners. TECHNOFORMA designs, manufactures and installs facades in GFRC, natural stone and porcelain stoneware, so the comparison below is a practitioner's view rather than that of a single-material seller. More on choosing a facade is in Facade design and selection.

Facade Design: Stages and Documents

Facade design and selection

Facade Design: Stages and Documents

Facade design is the development of a set of solutions and documents from which the facade will be manufactured and installed: from the architectural concept and choice of materials to working drawings of the substructure, cladding layout, details and specifications. For a ventilated rainscreen facade the design also includes calculations: wind load, cladding weight, anchor capacity, thermal performance.The main criterion of a good design is that it can be built without improvisation on the scaffold. If junctions, reveals and parapets are not detailed, installers resolve them on site, and that is exactly where leaks, cracks and efflorescence later appear.This article is for developers, general contractors, client-side technical managers and architects planning the schedule and budget of facade works. At TECHNOFORMA the design department consists of 12 designers led by two architects, as well as 3D visualisers; the design is developed together with manufacturing and installation. More on selection and design is in the section Facade design and selection.

Facade Architectural Concept: Where a Project Begins

Facade design and selection

Facade Architectural Concept: Where a Project Begins

A facade architectural concept is the first stage of a project, at which the image of the building is defined: composition, divisions, proportions, materials, colour and key details. The concept is presented as sketches, elevations and 3D visualisations; the client makes a decision on it, and designers then develop the working drawings.The main test of a good concept is that it can be built. An attractive image that cannot be manufactured in the required quantities, installed on the given wall or approved in the given city will have to be reworked, and the client loses time. So the concept should take materials, production technology and budget into account from the start.A concept is needed by developers of residential complexes and business centres, building owners refurbishing a facade, and architects who need the cladding worked out. At TECHNOFORMA concepts are prepared by the design department: 12 designers led by two architects, plus 3D visualisers. More on choosing and designing facades is in Facade design and selection.

Facade Works Estimate: Structure and Review

Facade design and selection

Facade Works Estimate: Structure and Review

A facade works estimate is a document that breaks the cost of a facade down into materials, labour, plant, overheads and the contractor's profit. It should be checked in two directions: completeness (are all items in the design included) and justification (do quantities match the design and rates match the market).The main mistake when checking is looking at the total or the price per square metre. Two estimates with the same total may describe different facades: one includes substructure, insulation and junctions, the other only cladding.This article is for developers, quantity surveyors, technical supervision and private clients who have received an estimate from a contractor. Other design-stage questions are covered in Facade design and selection.

Request a callback